ACCELERATED DROUGHT RESPONSE PROJECT

The Accelerated Drought Response Project (ADRoP) is a water storage project that will improve drought resilience for the existing County residents.

It will allow the San Benito CountyWater District (District) to store excess wet-year water in the local groundwater basin and recover those supplies during future droughts. ADRoP will include an expansion of the West Hills Water Treatment Plant, the construction of up to 5 aquifer storage and recovery wells (ASR Wells), and associated water transmission pipelines. The project is estimated to cost approximately $55 million. However, the District has secured $20 million in grant funding from the State and Federal governments, which will help limit rate impacts. The District continues to work on securing additional funding to further minimize rate impacts.

Water Supply Reliability

Helps meet drought demands.
Mitigates for reduced availability
of imported water in dry years

Improves Water Quality

Maintains high water quality
during droughts.

Local Control

Reduces reliance on state-
wide water delivery system.

Construction Schedule

West Hills Water Treatment Plant Expansion

May 2025 - August 2026

ASR Wells

July 2025 - January 2026

Pipelines

May 2025 - August 2026

Project Cost

The current construction cost estimate is $55 million. State and Federal grants will cover more than one third of project costs.

  • California Department of Water Resources: $13.7 million
  • U.S. Bureau of Reclamation: $6.7 million

 

Construction Impacts

West Hills Water Treatment Plant Expansion

Impacts will be minimal and will be limited to an insignificant increase in traffic on Union Road.

ASR Wells

Impacts will be minimal due to location in agricultural areas but has the potential to increase noise levels.

Pipelines

Moderate traffic impacts could result along San Felipe and Fallon Roads, potentially with one-way traffic controls.

Prior Master Plan Accomplishments

  • Lessalt Treatment Plant Upgrade
  • West Hills Treatment Plant
  • Hollister Wastewater Reclamation Facility
  • Ridgemark Wastewater Treatment Plant

 

2023 Master Plan – Key Findings

  • Current water supply is sufficient in normal and wet years
  • Deficit of 1,200 acre-feet per year in dry and critically dry years
  • Shortage exists for existing customers

 

2023 Master Plan – Key Recommendations

  • Implement the Accelerated Drought Response Project (ADRoP) to improve drought resilience
  • Build treated water transmission pipeline from West Hills Water Treatment Plant to San Juan Bautista

 

Accelerated Drought Response Project (ADRoP)

  • Implement the Accelerated Drought Response Project (ADRoP) to improve drought resilience
  • Build treated water transmission pipeline from West Hills Water Treatment Plant to San Juan Bautista


Purpose:

Provide a drought resilient water supply on an expedited timeline to qualify for grant funding.

 

Project Benefits:

Improves water supply reliability and water quality during droughts.

 

Project Components:

  • Expansion of West Hills Water Treatment Plant to 6.75 MGD
  • 4-5 wells for injection and extraction
  • New pipelines and appurtenances

 

Capital Cost:

Current estimate +/- $55 million

 

 

ADRoP Grant Funding

Grant Funding Target Grant Grant Award Match Required
DWR – IRWM $1.8M $1.8M 50%
DWR – SGMA Round 2 $20M $11.5M 0%
USBR – Small Storage $9.2M $6.7M 75%
Total Grant Funding $20M
  • Over 35% of the project will be funded through grants.
  • Eligible for another $6M in federal grant funding.

Stay Informed

 

District Contact:
Dana Jacobson, General Manager
Email: djacobson@sbcwd.com
Telephone: (831) 637-8218
Website: www.sbcwd.ca.gov

Get Project Updates
Translate »